2017-04-24 Project Management Meeting

Date

Attendees

Discussion items

ItemWhoNotes
RefApp 2.6Hillary Bagiire & raff
  • Release moving along on Talk
  • No evidence of blockers that we know of
RefApp 2.7Stephen Senkomago Musoke
  • Would like to start with similar process of 2.6: 3 big features and 4 small features
  • Approach it as "2 cycles" (one per quarter)
    • May - July
    • August - October
  • Consider a "priority and then find resources" approach instead of just a "here's what we can get done with what we have" approach
    • Identify stretch goals and then hunt for resources to make the impossible probably
  • How to decide on features? How do we get broad input on priorities?
    • Ask implementations
      • Scrum of scrums
      • Survey
      • Call out on Talk
      • Reach out to individual implementations for one-on-one discussion
    • Infrastructure Priorities
      • Continue migration to OWA (Angular/React) from GSP
        • Adopting Bootstrap & new Style Guide
        • Metadata management
      • External Configuration
      • New approach to sync
      • Improvements to Reporting
        • ETL (may not fit in RefApp)
    • GSoC projects
PlatformBurke Mamlin
  • raff released 2.0.5
  • Core 2.1 beta released last week
AddonsDarius JazayeriDeferred (Darius not available today)
InternshipsHarsha Kumara & Kaweesi Joseph
  • GSoC in good shape
AndelaDaniel Kayiwa
  • Progress going well
  • Did demo last week
  • Could benefit from a mid-experiment meetup between Andela & OpenMRS to do a retrospective and assess expectations on both sides
Scrum of ScrumsDarius JazayeriDiscuss next week
PM Tool 
  • FM-193 needs to get on a design forum

Action items

  • Burke Mamlin to ask Michelle to set up a meetup between Andela & OpenMRS (Daniel, Jan, Darius ± others on OpenMRS side)
  • Burke Mamlin will post to Talk about getting FM-193 on a design forum with Suranga or Harsha
  • Daniel Kayiwa to f/u on security discussion with Isaac Sears