2015-10-19 Project Management Meeting

Date

Attendees

Goals

Discussion items

ItemWhoNotes

Reference Application 2.3 

Tharunya Pati
Platform 1.12Shruthi Dipali & Sathyan
  • Shruthi and Bahmni Project Manager Sathyan will be pairing to be the release managers for 1.12
  • Need to talk with release managers about what all will go into 1.12
  • 1.12 will focus on drug entry and order sets
Platform 2.0Mayank Sharma
  • Week of October 19 all hands on deck to work on remove legacy UI - https://talk.openmrs.org/t/update-on-moving-legacy-ui-to-a-module/3327
  • Wyclif working on tickets to have a sprint later this week.
  • Darius recommends getting the first part of the coding done and then ask for people to help create tickets
  • Planning on merging in all initial work for removing deprecated methods this week (10/19) Daniel Kayiwa will be taking the first pass.
Implementations 
  • PIH is investing more time looking at Bahmni distribution as a long term solution.
  • Registration is live in Mirebalais and we are registering patients.

Action items

  • All will have conversation about James Arbaugh's observation  during UAT testing to get a strategy for handling it  Unable to locate Jira server for this macro. It may be due to Application Link configuration.
  • Burke Mamlin will check in with Tharunya Pati to see if she needs any help getting the release out this week.
  • Mayank Sharma will make a Talk post around moving 2.0 forward to coordinate.
  • Mayank Sharma will make sure we are taking a look at legacy documentation to update language around platform vs. reference application where necessary. May be good to talk w/ Michael Downey.