OpenMRS OCL Client Sprint 6

General Information 

Team Lead: Daniel Kayiwa

Sprint Lead:  Shakira Ndagire Seruwagi


Timeline

Start Date: 25th July 2018

End Date: 8th August 2018

Participants 

  • Kyampeire Hadijah
  • Christopher Kalule
  • Rurangirwa Bailly

  • Emmanuel Ndukwe
  • Shakira Ndagire Seruwagi

Sprint Goals

The main goal of this sprint is to ensure the following from the Open Concept Lab MVP are implemented;

  • Add concepts from Bulk Concepts to an implementation dictionary

  • Implement the feedback given during the Sprint 5 demo.

Sprint Dashboard

key summary type created updated due assignee reporter priority status resolution

Unable to locate Jira server for this macro. It may be due to Application Link configuration.

How To Participate

Add your name to the list on this wiki page (with any comments about your availability). If you want to join after the sprint has started just join the IRC channel mentioned above and say hello.

The general process:

  1. New to OpenMRS sprints? Want help getting started? Join IRC and say "???": I'd like to participate in the sprint!". If you get no response, just ping any of the above sprint participants as per the IRC tips at http://en.flossmanuals.net/openmrs-developers-guide/support/
  2. Pick a ticket from the available tickets in the top-left of the sprint dashboard page at:
    • Make sure it does not depend on a ticket that is incomplete.
  3. If you have any questions about the ticket, ask on the group chat.
  4. Do the ticket. See our HOWTO for git. Sprint specific git HOWTO for devs with push rights: whatever works for you :-) If you don't like pull requests, don't send them. Commit and push directly to the main repo. If you do like pull requests, fork the main repo and send pull requests, but merge them right after. My favorite way is to work on the main repo, but create local branches (without pushing them to the main repo). Merge branches locally to the master and push to the main repo.
  5. Join the daily scrum to share your updates

During Project Notes for the sprint

To be added while the project progresses 

Sprint Retrospective:

To be added after the end of the sprint. 

Resources

JIRA board: https://issues.openmrs.org/secure/RapidBoard.jspa?rapidView=170&projectKey=OCLOMRS&view=detail&selectedIssue=OCLOMRS-97

Github repo: https://github.com/openmrs/openmrs-ocl-client