Attendees
Discussion items
Project Activities Spreadsheet
Item | Who | Notes |
---|
GCI | @suthagar23 & @Reuben Varghese | - Burke Mamlin will make sure admins have access to prior applications and admins are decided in next 24-48 hours
|
Internships: Andela | | |
Sync 2.0 (SolDevelo, Jembi) | | - Daniel Futerman will ask folks leading from Jembi side to reach out to Cynthia Antwi to give her a point of contact on Jembi side for Sync work.
- Cynthia Antwi to follow up with Jembi in the call on the 18th regarding this activity.
|
OpenMRS Reference Application 2.9 | | |
OpenMRS Platform 2.2 | | - September 2018 release date (estimate 2-3 weeks of work left on remaining tickets)
- Can see where things stand on the Technical Roadmap
- Platform tickets will be done tentatively by next week (20 Sept) so Platform release can proceed
|
Technical Road Map Process |
| - Having discussions on how to (re)define a roadmap process that will work better for the community.
- Has spoken with Paladium
- Talking to AMPATH this week
- Planning to post invite on Global Health mailing list
- Planning on getting input prior to Scrum of Scrums on 11 September.
- Cynthia is leading effort in defining the process and is reaching out to various parties to get their input.
- Cynthia putting a call out for volunteer business analysts this week
- Having fun trying to reach people during the holidays
- Goal is to have a draft document by 31 August
- Will plan to get Doodle poll for Scrum of Scrums date out this week
|
Reference Application priorities | Stephen Senkomago Musoke | - It would help to have a style guide (bootstrap+++) to guide developers on how, for example, to style diagnoses, etc.
- Cynthia Antwi pointed out that we need to know process for discussing/deciding these things
- Burke Mamlin suggested we use the opportunity to refactor login+landing+patient dashboard in React (a react+bootstrap style guide could come out of the process)
- Darius Jazayeri pointed out the risk of creating yet another UI that competes with others. Instead, we should "pull" from existing efforts rather than "push from center"
- Cynthia Antwi pointed out countries don't necessarily know the plans for addressing UI going forward
|
PM tool |
| - Try to look at this weekly.
- Do we have a JIRA project for it?
|
AOB |
| - Scrum of Scrums - scheduled for Thursday, 13 September (announcement)
- Last couple weeks of todos
- Cynthia to work with Dan on developing plan/process on how to transition work from GSoC into community development
- Relook at the 'technical needs' that may need core technical support
|
Next week |
|
|
Action items
- follow up on GCI to ensure that we submit the application by September 17
- propose reinvention of the 'release process'