2015-03-16 Project Management Meeting

Date

Mar 16, 2015

Attendees

Goals

  • Help finalize open items for 2.2.

Discussion items

ItemWhoNotes
OpenMRS 2.2
  • Drug Look Up - Wyclif Luyima (taking on
    Error rendering macro 'jira' : Unable to locate Jira server for this macro. It may be due to Application Link configuration.
    ) create list of concepts to send to Andy then Wyclif will finish up this week 16 March
  • OpenMRS 2.2 is now running on top of 1.11. URL is not working and is a blocker Unable to locate Jira server for this macro. It may be due to Application Link configuration.
  • Condition list in code review. Darius has releasd emrapi and there is some code in there but condition list will not be part of OpenMRS 2.2 as not all code is complete. Three tickets still in progress Unable to locate Jira server for this macro. It may be due to Application Link configuration.
  • Registration - would like to get Unable to locate Jira server for this macro. It may be due to Application Link configuration.  done by 2.2 release if possible. If not, then it will be in 2.2.1.
  • Appointment Scheduling - David tested and is now running on top of 1.11.1. OpenMRS reference demo data has example demo types.
  • Chart Search appears to be working well. Would like to try and verify performance implications since there were changes made to the class loader? Daniel will try to explain changes made over email.
  • Migration Strategy Unable to locate Jira server for this macro. It may be due to Application Link configuration. Wyclif Luyima will work on migration strategy after appointment scheduling. Initial goal is to enumerate any potential challenges going from OpenMRS 1.9 to 2.2.
Reference Application Distribution 
  • CI for running distribution and running test is not working properly
  • Need to rename devtest01 as it is actually being used for quality assurance

 

Action items